The invention relates to a ship loader cantilever crane repairing and chute tube mounting method. The method comprises the following steps that firstly, cantilever crane firework correction construction is prepared; step 2, carrying out hot work correction on the cantilever crane; step 3, track replacement; fourthly, the sliding cylinder is installed, damaged parts are replaced before installation, and assembly of all the parts of the sliding cylinder system is completed on the ground; during installation, hoisting equipment is used for hoisting to an installation position, the chute tube is hung, and the variable-amplitude hydraulic cylinder is connected through a flange bolt part. By designing a standardized boom repair process, the repair of the deformed part of the boom is facilitated, the chute tube is relatively flexible and convenient to mount, the maintenance steps are clear, and the overall maintenance working efficiency is high.
本发明是一种装船机臂架修复及溜筒安装方法,包括以下步骤:步骤一:臂架火工校正施工准备;步骤二:对臂架进行火工校正;步骤三:轨道更换;步骤四:溜筒安装,安装前,替换损坏的部件,并在地面完成溜筒系统各部件组装;安装时采用吊装设备吊装至安装位置,将溜筒悬挂,变幅液压缸,通过法兰螺栓部件进行连接。本发明通过设计标准化的臂架修复工艺,方便臂架变形处的修复,且溜筒安装相对灵活方便,维修步骤条理清晰,整体维修工作效率高。
Method for repairing boom of ship loader and installing chute tube
一种装船机臂架修复及溜筒安装方法
2023-05-23
Patent
Electronic Resource
Chinese
European Patent Office | 2024
|European Patent Office | 2024
|European Patent Office | 2023
|European Patent Office | 2023
|European Patent Office | 2023
|