The invention discloses an angle control method for integrated building of a ship anchor platform. The method comprises the steps that foundation lines and trepanning construction are conducted; hoisting the hawse pipe; the hawse pipe positioning and angle verification comprises the steps that the hawse pipe is inserted into a deck to be folded to complete positioning, and after the hawse pipe is welded, an anchor mouth and an anchor table are positioned; the anchor mouth and the anchor table are positioned and verified, and it is guaranteed that the hawse pipe slope and the anchor table panel are located in the same plane. According to the method, the precision quality of the anchor mouth and anchor platform integrated construction anchoring system angle is ensured, the cost is reduced, and the production efficiency is improved.
本发明公开了一种船舶锚台一体化建造角度控制方法,包括:基础线条与开孔施工;对锚链筒进行吊装;所述锚链筒定位与角度验证,将所述锚链筒插入到甲板进行对合完成定位,所述锚链筒焊接完成后进行锚唇锚台定位;锚唇锚台定位与验证,保证锚链筒斜面与锚台面板在同一平面内。本发明确保了锚唇锚台一体化建造下锚系角度的精度质量,降低了成本,提高了生产效率。
Angle control method for integrated construction of ship anchor platform
船舶锚台一体化建造角度控制方法
2025-05-06
Patent
Electronic Resource
Chinese
IPC: | B63B Schiffe oder sonstige Wasserfahrzeuge , SHIPS OR OTHER WATERBORNE VESSELS |
Ship integrated window cleaning platform, construction method and ship
European Patent Office | 2024
|Control method for realizing zero-allowance hoisting of ship anchor platform