The purpose of this paper is to examine the initial acceptance test experience of certain pieces of auxiliary equipment of the Fast Flux Test Facility (FFTF). The scope focuses on the DHX blowers and drive train, inert gas blowers, H and V containment isolation valves, and the Surveillance and In-service Inspection (SISI) transporter and trolley. For each type of equipment, the discussion includes a summary of the design and system function, installation history, preoperational acceptance testing procedures and results, and unusual events and resolutions. (ERA citation 04:051640)
Initial Acceptance Test Experience with FFTF Plant Equipment
1978
35 pages
Report
Keine Angabe
Englisch